About Mathematics

Mathematics MCQs for recruitment exams often ask you to apply familiar ideas quickly: percentages, ratios, averages, fractions, algebra, geometry, and word problems. Begin by deciding what the question is asking you to find, then write down the quantities and units. Before choosing an answer, check the direction and approximate size of the result. A quick estimate can catch a misplaced decimal or a reversed ratio.

Learn each method through problems with different wording. A percentage increase depends on the original value, while a percentage decrease may use a different starting point. In a work-rate problem, two people completing a task together contribute rates rather than adding their completion times. Small comparisons like these are more useful than memorising an isolated formula.

Start with short, untimed sets. After each error, mark whether you misunderstood the question, chose the wrong operation, or made an arithmetic slip. Then redo the problem without looking at the solution. As you build accuracy, switch to timed mixed sets and practise leaving a lengthy question for later. Review the syllabus for your post so your practice includes the methods and difficulty level you are likely to see.

Browse sections
All MCQs All Mathematics questions

Mathematics Questions

Clear filters

7247 matching questions

A and B can do a piece of work in 12 days, B can C in 8 days and C and A in 6 days. How long would B take to do the same work alone?

  • A24
  • B32
  • C30
  • D48
Show answerHide answer

Correct answer D

Given: Time taken by A and B to complete the work = 12 days Time taken by Band C to complete the work = 8 days Time taken by C and A to complete the work = 6 days Formulae used: Time = Total work / Efficiency Calculation: Let us assume the total work is 1 unit. ⇒ A and B complete 1 unit work in 12 days → (A and B)'s 1 day's work = 1/12 ⇒ Band C complete 1 unit work in 8 days → (Band C)'s 1 day's work = 1/ 8 ⇒ A and C complete 1 unit work in 6 days → (A and C)'s 1 day's work = 1/ 6 Adding everyone's 1 day's work: ⇒ 2 ( A + B + C ) =( 1/12 ) +(1/ 8) +(1/ 6) ⇒ A + B + C =9/48 = A, B, and C's 1 day's work = 9/48 ⇒ B's 1 day's work = ( A + B + C ) − ( A + C ) ⇒ B's 1 day's work =(9/48) −(1/6) = 9-8 x/48 = 1/ 48 ⇒ B completes 1/ 48 of the work in 1 day. Therefore, B alone will take 48 days to complete the work.

If actual cost is high but earned value is low, the project status is?

  • AUnder budget and ahead of schedule
  • BOver budget and behind schedule
  • COn budget and on schedule
  • DCannot determine
Show answerHide answer

Correct answer B

Actual Cost (AC) measures money spent so far. Earned Value (EV) measures the value of work actually completed. If AC > EV, the project is spending more than the value earned → over budget. If EV is low, less work is completed than planned → behind schedule.

How many subsets does the set {1, 2, 3, 4, 5} have?

  • A32
  • B16
  • C25
  • DNone of these
Show answerHide answer

Correct answer A

For any set, we count subsets using powers of 2. Rule If a set has n elements, then Number of subsets = 2^n Reason For each element you have exactly 2 choices: 1. Put it in the subset 2. Leave it out With 5 elements, total choices = 2 × 2 × 2 × 2 × 2 = 2^5 Apply to {1, 2, 3, 4, 5} n = 5 Number of subsets = 2^5 = 32 That 32 includes: 1. The empty set: {} 2. All sets with 1 element, 2 elements, 3 elements, 4 elements 3. The set itself: {1, 2, 3, 4, 5}.

What is 25% of 200?

  • A40
  • B45
  • C50
  • D55
Show answerHide answer

Correct answer C

25% of 200 is calculated by multiplying 200 by 25/100, which equals 50.

Have a useful question? Submit an MCQ