If actual cost is high but earned value is low, the project status is?

  • AUnder budget and ahead of schedule
  • BOver budget and behind schedule
  • COn budget and on schedule
  • DCannot determine
Show answerHide answer

Correct answer B

Actual Cost (AC) measures money spent so far. Earned Value (EV) measures the value of work actually completed. If AC > EV, the project is spending more than the value earned → over budget. If EV is low, less work is completed than planned → behind schedule.