About Mathematics

Mathematics MCQs for recruitment exams often ask you to apply familiar ideas quickly: percentages, ratios, averages, fractions, algebra, geometry, and word problems. Begin by deciding what the question is asking you to find, then write down the quantities and units. Before choosing an answer, check the direction and approximate size of the result. A quick estimate can catch a misplaced decimal or a reversed ratio.

Learn each method through problems with different wording. A percentage increase depends on the original value, while a percentage decrease may use a different starting point. In a work-rate problem, two people completing a task together contribute rates rather than adding their completion times. Small comparisons like these are more useful than memorising an isolated formula.

Start with short, untimed sets. After each error, mark whether you misunderstood the question, chose the wrong operation, or made an arithmetic slip. Then redo the problem without looking at the solution. As you build accuracy, switch to timed mixed sets and practise leaving a lengthy question for later. Review the syllabus for your post so your practice includes the methods and difficulty level you are likely to see.

Browse sections
All MCQs All Mathematics questions

Mathematics Questions

Clear filters

7247 matching questions

One Mile is equal to how many foot?

  • A5240
  • B5260
  • C5290
  • D5280
Show answerHide answer

Correct answer D

A mile is a unit of distance. It is equal to 5,280 feet or exactly 1.609344 kilometers. 1 km = 0.62137119 miles 0.62137119 miles ∼ 0.62 miles ∴ 1 km = 0.62 miles Key facts: Miles to Kilometres = Miles × 8/5 (Approximately) Kilometers to Miles = Km × 5/8 (Approximately).

If +5 means profit of Rs. 5, then -5 means?

  • ASale of Rs. 5
  • BLoss of Rs. 5
  • CPurchase of Rs. 5
  • DNone of these
Show answerHide answer

Correct answer B

Positive sign (+) indicates profit, so +5 means profit of Rs. 5. Negative sign (−) indicates loss, so −5 means loss of Rs. 5.

Asian's weight increased by 25% from year 2005 to 2009. If his weight was k kilograms in 2009, what was it in 2004?

  • A0.80k
  • B1.75k
  • C1.25k
  • DNone of these
Show answerHide answer

Correct answer A

Asian's weight increased by 25% from 2005 to 2009. This means his weight in 2009 is 125% of his weight in 2005: Weight in 2009 = 1.25 × Weight in 2005 Given his weight in 2009 is k kilograms: k = 1.25 × Weight in 2005 To find his weight in 2005: Weight in 2005 = k / 1.25 = 0.8k Since the question asks for his weight in 2004, and we don't have any information about changes in 2004: Weight in 2004 is assumed to be the same as Weight in 2005.

What is the factorized form of the expression: x² + 5x + 4?

  • A(x + 4)(x + 1)
  • B(x + 3)(x + 2)
  • C(x + 5)(x - 1)
  • DNone of these
Show answerHide answer

Correct answer A

To factorize the expression x² + 5x + 4, find two numbers that multiply to 4 and add up to 5. Step 1: Find the numbers The numbers are 4 and 1, since 4 * 1 = 4 and 4 + 1 = 5. Step 2: Factorize the expression x² + 5x + 4 = (x + 4)(x + 1).

Price of 2 pens and 3 pencils is 86, the price of 4 pens and 1 pencil is 112. Find the price of a pen?

  • A25
  • B18
  • C12
  • D15
Show answerHide answer

Correct answer A

Let's set up the equations based on the given information: 1. 2p + 3c = 86 (Equation 1) 2. 4p + 1c = 112 (Equation 2) where p is the price of a pen and c is the price of a pencil. To solve for p and c, we can use substitution or elimination. Let's use the elimination method. First, solve Equation 2 for c: 4p + c = 112 c = 112 - 4p Now, substitute this expression for c into Equation 1: 2p + 3(112 - 4p) = 86 2p + 336 - 12p = 86 2p - 12p = 86 - 336 -10p = -250 p = 25 So, the price of a pen is 25.

If 15 workers can complete a job in 20 days, how many workers are required to complete the same work in 10 days, assuming all workers have equal efficiency?

  • A30
  • B32
  • C34
  • DNone of these
Show answerHide answer

Correct answer A

Given: 15 workers complete the work in 20 days Step 1: Find total work Total work = Number of workers x Number of days Total work = 15 x 20 = 300 Step 2: Find workers needed for 10 days Let the required number of workers = W W x 10 = 300 W = 300 / 10 W = 30 Verified & Updated.

Have a useful question? Submit an MCQ