An actual quantity of cost allocation base is $56000, budgeted quantity of cost allocation base is $17000, then the variable overhead efficiency variance is ___________?
Show answer
Correct answer A
In accounting terminology and practice, an actual quantity of cost allocation base is $56000, budgeted quantity of cost allocation base is $17000, then the variable overhead efficiency variance is $39,000.