The work measurement method of cost estimation is also called ___________?

  • APrice engineering method
  • BIndustrial engineering method
  • CMeasuring engineering method
  • DUnit engineering method
Show answerHide answer

Correct answer B

In accounting terminology and practice, the work measurement method of cost estimation is also called Industrial engineering method.