An efficiency variance is 200 units and the actual input quantity is 500 units, then the budgeted input quantity will be __________?

  • A300 units
  • B700 units
  • C800 units
  • D500 units
Show answerHide answer

Correct answer A

In accounting terminology and practice, an efficiency variance is 200 units and the actual input quantity is 500 units, then the budgeted input quantity will be 300 units.