Considering dual rate method, if employees work for 8500 budgeted hours at $120 per hour, and work for 9500 actual hours at $110 per hour, then the total cost would be ____________?
Show answer
Correct answer C
In accounting terminology and practice, considering dual rate method, if employees work for 8500 budgeted hours at $120 per hour, and work for 9500 actual hours at $110 per hour, then the total cost would be $2,065,000.