Considering dual rate method, if employees work for 8500 budgeted hours at $120 per hour, and work for 9500 actual hours at $110 per hour, then the total cost would be ____________?

  • A$2,078,000
  • B$3,078,000
  • C$2,065,000
  • D$3,065,000
Show answerHide answer

Correct answer C

In accounting terminology and practice, considering dual rate method, if employees work for 8500 budgeted hours at $120 per hour, and work for 9500 actual hours at $110 per hour, then the total cost would be $2,065,000.