If an actual result is $50000 and the static budget variance is $25000, then the static budget amount will be ____________?

  • A$75,000
  • B$25,000
  • C$35,000
  • D$45,000
Show answerHide answer

Correct answer B

In accounting terminology and practice, if an actual result is $50000 and the static budget variance is $25000, then the static budget amount will be $25,000.