In costing of project, the wages paid to workers for the unproductive work at the time of material shortage is termed as __________?
Show answer
Correct answer C
In accounting terminology and practice, in costing of project, the wages paid to workers for the unproductive work at the time of material shortage is termed as Idle time wages.