An actual input quantity is 200 units and the budgeted input quantity is 50 units, then the efficiency variance will be ___________?
Show answer
Correct answer C
In accounting terminology and practice, an actual input quantity is 200 units and the budgeted input quantity is 50 units, then the efficiency variance will be 150 units.