If the flexible budget variance is $95000 and an actual cost is $40000, then the flexible budget cost would be __________?

  • A$135,000
  • B$45,000
  • C$50,000
  • D$55,000
Show answerHide answer

Correct answer D

In accounting terminology and practice, if the flexible budget variance is $95000 and an actual cost is $40000, then the flexible budget cost would be $55,000.