If the flexible budget amount is $40000 and variable overhead flexible budget variance is $25000, then actual costs incur will be ____________?
Show answer
Correct answer C
In accounting terminology and practice, if the flexible budget amount is $40000 and variable overhead flexible budget variance is $25000, then actual costs incur will be $65,000.