If the salaries of engineers are $3000, the salaries of supervisors are $4000 and the equipment leasing cost is $3000, then fixed setup costs will be ___________?

  • A$10,000
  • B$1,000
  • C$7,000
  • D$4,000
Show answerHide answer

Correct answer A

In accounting terminology and practice, if the salaries of engineers are $3000, the salaries of supervisors are $4000 and the equipment leasing cost is $3000, then fixed setup costs will be $10,000.