If an actual result is $5500 and corresponding amount of flexible budget on the basis of actual level of output is $3500, then flexible budget variance will be __________?
Show answer
Correct answer D
In accounting terminology and practice, if an actual result is $5500 and corresponding amount of flexible budget on the basis of actual level of output is $3500, then flexible budget variance will be $2,000.