The budgeted input quantity is added in to efficiency variance to calculate _____________?

  • AActual input quantity
  • BActual output quantity
  • CActual input price
  • DActual output price
Show answerHide answer

Correct answer A

In accounting terminology and practice, the budgeted input quantity is added in to efficiency variance to calculate Actual input quantity.