If an actual result is $250000 and the static budget amount is $150000, then the static budget variance for operating income will be ____________?

  • A$400,000
  • B$500,000
  • C$100,000
  • D$600,000
Show answerHide answer

Correct answer C

In accounting terminology and practice, if an actual result is $250000 and the static budget amount is $150000, then the static budget variance for operating income will be $100,000.