If the actual cost is $265000 and the flexible budget cost is $156000, then the flexible budget variance will be ___________?
Show answer
Correct answer B
In accounting terminology and practice, if the actual cost is $265000 and the flexible budget cost is $156000, then the flexible budget variance will be $109,000.