If the actual cost is $265000 and the flexible budget cost is $156000, then the flexible budget variance will be ___________?

  • A$409,000
  • B$109,000
  • C$209,000
  • D$309,000
Show answerHide answer

Correct answer B

In accounting terminology and practice, if the actual cost is $265000 and the flexible budget cost is $156000, then the flexible budget variance will be $109,000.