If an actual result in static budget is $2500 and the corresponding budgeted amount is $2200, then the static budget variance will be __________?

  • A$3,000
  • B$300
  • C$4,700
  • D$4,500
Show answerHide answer

Correct answer B

In accounting terminology and practice, if an actual result in static budget is $2500 and the corresponding budgeted amount is $2200, then the static budget variance will be $300.