If an actual result in static budget is $2500 and the corresponding budgeted amount is $2200, then the static budget variance will be __________?
Show answer
Correct answer B
In accounting terminology and practice, if an actual result in static budget is $2500 and the corresponding budgeted amount is $2200, then the static budget variance will be $300.