A project should be accepted if its internal rate of return exceeds _____?

  • AThe rate of return on a government bond
  • BZero
  • CThe rate the company pays on borrowed funds
  • DThe company's required rate of return
Show answerHide answer

Correct answer D

A project should be accepted if its internal rate of return (IRR) exceeds the company's required rate of return. This indicates that the project is expected to generate returns higher than the company's minimum acceptable return, making it a potentially profitable investment.