Project invisibility can lead to sub-optimal results when ______ is used for capital retaining.

  • ANPV
  • BARR
  • CIRP
  • DPI
Show answerHide answer

Correct answer A

NPV (Net Present Value) Reason: Project indivisibility can cause sub-optimal results when NPV is used for capital rationing. NPV ranking may not give the best combinatio n of projects when projects cannot be divided and capital is limited.