In a joint-product costing decision, which cost is generally irrelevant when deciding whether to process a product further after the split-off point?

  • AAdditional processing cost incurred after the split-off point
  • BAdditional selling revenue earned after further processing
  • CJoint cost incurred before the split-off point
  • DNone of these
Show answerHide answer

Correct answer C

Joint costs are incurred before the products reach the split-off point. These costs are common to the joint products and cannot be avoided by choosing further processing. Further-processing decisions should compare additional revenue with additional processing cost.