Calculate the amount of direct labor if: Direct material = 15,000; Direct labor = 70% of prime cost?

  • A30,000
  • B10,500
  • C35,000
  • DNone of these
Show answerHide answer

Correct answer C

Let Direct labor = x Prime cost = Direct material + Direct labor Prime cost = 15,000 + x Direct labor = 70% of Prime cost x = 70% of (15,000 + x) x = 0.7 (15,000 + x) x = 10,500 + 0.7x x - 0.7x = 10,500 0.3x = 10,500 x = 10,500 / 0.3 x = 35,000.