The labor rate variance is determined by multiplying the difference between the actual labor rate and the standard labor rate by ______?

  • AThe standard hours allowed.
  • BThe actual hours worked.
  • CThe budgeted hours allowed.
  • DNone of these.
Show answerHide answer

Correct answer B

Labor rate variance measures the difference between the actual labor cost and the expected (standard) labor cost. It is calculated as: (Actual Rate – Standard Rate) × Actual Hours Worked Since the actual hours worked determine the total variance, they are used in the calculation.