The labor rate variance is determined by multiplying the difference between the actual labor rate and the standard labor rate by ______?
Show answer
Correct answer B
Labor rate variance measures the difference between the actual labor cost and the expected (standard) labor cost. It is calculated as: (Actual Rate – Standard Rate) × Actual Hours Worked Since the actual hours worked determine the total variance, they are used in the calculation.