If the Net Present Value (NPV) of a project is positive, what should the company generally do?

  • AAccept the project because it adds financial value
  • BPostpone the project until its NPV becomes zero
  • CReject the project because it has no future cash flows
  • DNone of these
Show answerHide answer

Correct answer A

Positive NPV means the present value of cash inflows exceeds the initial and other relevant cash outflows. It indicates that the project is expected to add value to the company. Under the NPV decision rule, a positive-NPV project is generally accepted.