15 men were hired to plough a piece of land in 10 days. How many more men will be required to do the same job in 3 days?
Show answer
Correct answer A
Total man-days = 15 × 10 = 150. To finish in 3 days requires 150 / 3 = 50 men, which is 50 - 15 = 35 more men.