20 men can construct a building in 40 days. How long will it take 10 men to do this work?

  • A50 days
  • B60 days
  • C70 days
  • D80 days
Show answerHide answer

Correct answer D

20 men can construct a building in 40 days. Total work = 20 men × 40 days = 800 man-days. Time = Total work / Number of men = 800 man-days / 10 men = 80 days.