If 10 men can construct a building in 40 days. How long will it take 20 men to do this work?

  • A20 days
  • B30 days
  • C40 days
  • D50 days
Show answerHide answer

Correct answer A

10 men = 40 days 1 man = 10 × 40 = 400 days 20 men = 400/20 = 20 days.