A completes a work in 12 days whereas B completes the same work in 24 days. If both A and B work together, the work will be completed in ____?
Show answer
Correct answer B
A completes the work in 12 days. So, A's 1-day work: 1/12 B completes the work in 24 days. So, B's 1-day work: 1/24 Together, their 1-day work: 1/12 + 1/24 LCM of 12 and 24 = 24: 2/24 + 1/24 = 3/24 = 1/8 Therefore, they will complete the whole work in: 8 days *.