If 70 men dig 630 m³ of soil in 5 days, in the same proportion, 80 men can dig the quantity of soil in 10 days?
Show answer
Correct answer A
Calculating the Rate of Work per Man per Day Rate = 630/70 × 5 = 630/350 = 1.8 m³/man/day Calculating the Quantity of Soil for 80 Men in 10 Days Quantity = 80 men × 10 days × 1.8 m³/man/day = 80 × 10 × 1.8 = 1440 m³.