A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work was finished one day earlier. How many days would it have been delayed if 5 more men were not employed?

  • A4 day
  • B2 day
  • C1 day
  • DNone of these
Show answerHide answer

Correct answer C

3 5 men completed the remaining job in 1 2 d a y s. Now the same job has to be done by 3 0 m e n. We know that, M 1 D 1 = M 2 D 2 Required time = 3 0 3 5 × 1 2 = 1 4 d a y s Delayed time = ( 1 4 − 1 3 ) = 1 d a y.