39 persons can repair a road in 12 days, working 5 hours a day. In how many days will 30 persons, of same efficiency working 6 hours a day, complete the work?

  • A13
  • B14
  • C15
  • DNone of these
Show answerHide answer

Correct answer A

Let's calculate the total man-hours required to complete the work: 39 persons * 5 hours/day * 12 days = 2340 man-hours If 30 persons work 6 hours a day: Let x be the number of days they need to complete the work: 30 persons * 6 hours/day * x days = 2340 man-hours 180x = 2340 x = 13.