If 6 men take 9 days to complete a work, how many men can complete the work in 3 days?

  • A18 men
  • B12 men
  • C9 men
  • DNone of these
Show answerHide answer

Correct answer A

If 6 men take 9 days, total work = 6 × 9 = 54 man-days. To finish in 3 days, number of men needed = 54 ÷ 3 = 18 men.