If 24 employees can complete a project in 20 days. The number of employees required to complete the project in 40 days is ______?
Show answer
Correct answer A
Inverse proportion: more days, fewer employees 24 employees × 20 days = x employees × 40 days x = (24 × 20)/40 x = 12.