If 20 labourers complete a piece of work in 8 days and after 4 days, 8 labourers leave the job, how much work has already been completed?
Show answer
Correct answer A
Total work = Number of labourers x Total days Total work = 20 x 8 = 160 units Work done in first 4 days = 20 labourers x 4 days Work done = 80 units Fraction of work completed = Work done / Total work = 80 / 160 = 1 / 2 Verified & Updated.