10 workers complete work in 40 days, 20 workers complete work in how many days?

  • A10 days
  • B20 days
  • C5 days
  • DNone of these
Show answerHide answer

Correct answer B

We are given that 10 workers complete the work in 40 days. Step 1: Find total work in worker-days Total work = 10 workers × 40 days = 400 worker-days Step 2: Find time for 20 workers Time required = 400 worker-days ÷ 20 workers = 20 days.