120 men are used to build huge building for 30 days. How long will it take 80 men to do the same work?

  • A50 days
  • B35 days
  • C40 days
  • D45 days
Show answerHide answer

Correct answer D

120 men can do work = 30 days 1 man can do this work = 120 x 30 = 3600 days 80 men can do this work = 3600/80 = 45 days.