If 70 men can work in 35 days, 40 men complete this work in days?

  • A40
  • B50
  • C61.25
  • D80.50
Show answerHide answer

Correct answer C

Find how many man-days to complete the road: 70*35 = 2450 man-days Let d = days required for 40 men to do it. 40d = 2450 d = 40 2450 = 61.25.