If 40 men build 4 buildings in 12 months how many men would be required to build 6 houses in 4 months?

  • A114 men
  • B140 men
  • C180 men
  • D160 men
Show answerHide answer

Correct answer C

If 40 men can build 4 buildings in 12 months we can divide 4/12 which is 1/3. 40*3 is 120 men for 4 buildings and 120 is divided into 4 we get 30 men for 1 building. so for buildings 30*2 = 60 120+60 is = 180.