The bridge is completed in 45 days by 105 men. How it will take 90 men to do the work?

  • A52 1/2
  • B60
  • C61
  • DNone of these
Show answerHide answer

Correct answer A

105 men complete the work in 45 days Total work = 105 men * 45 days = 4725 man-days Now, 90 men will complete the work: 4725 man-days / 90 men = 52.5 days.