During a Haj field-operation scheduling exercise, a worker serves two duty days then rests one, repeating until seven duty days are complete. The first duty day is Monday. Which weekday is the seventh?
Show answer
Correct answer B
Pattern: 2 duty days, 1 rest day, repeat until 7 duty days are done. First duty day = Monday Let’s list them: Day 1: Monday → Duty 1 Day 2: Tuesday → Duty 2 Day 3: Wednesday → Rest Day 4: Thursday → Duty 3 Day 5: Friday → Duty 4 Day 6: Saturday → Rest Day 7: Sunday → Duty 5 Day 8: Monday → Duty 6 Day 9: Tuesday → Rest Day 10: Wednesday → Duty 7 The 7th duty day is Wednesday.