If four workers can complete a job in 8 hours, the same job can be completed by six workers in ______?

  • A5 hours 50 minutes
  • B4 hours 50 minutes
  • C5 hours 20 minutes
  • DNone of these
Show answerHide answer

Correct answer C

Step 1: Calculate the total work hours for four workers Total work hours = 4 workers × 8 hours = 32 worker-hours Step 2: Calculate the time required for six workers Time = Total work hours / Number of workers = 32 worker-hours / 6 workers = 5.33 hours = 5 hours 20 minutes.