10 people complete a work in 14 days. 4 persons will complete this work in how many days?

  • A28 days
  • B30 days
  • C35 days
  • DNone of these
Show answerHide answer

Correct answer C

Total work = 10 × 14 = 140 person-days Days needed by 4 persons = 140 ÷ 4 = 35 days.