If 12 men work 8 hours a day to complete a work in 10 days, how many men working 12 hours a day can complete the work in 5 days?
Show answer
Correct answer C
To solve this problem, calculate the total hours worked by the men: 12 men × 8 hours/day × 10 days = 960 hours Now, find the number of men needed to complete the work in 5 days, working 12 hours a day: Let x be the number of men. x men × 12 hours/day × 5 days = 960 hours x × 60 = 960 x = 16.