If 25 workers can complete a task in 30 days, the number of workers required to complete the task in 15 days is _____?

  • A35
  • B45
  • C50
  • DNone of these
Show answerHide answer

Correct answer C

Let's solve this inverse proportion problem. 25 workers × 30 days = x workers × 15 days x = (25 × 30) / 15 x = 50.