The bridge is completed in 20 days by 80 men. How long will it take 70 men to complete the work?

  • A29 days
  • B26 days
  • C22.86 days
  • D27 days
Show answerHide answer

Correct answer C

Step 1: Find total work in man-days 80 men complete the bridge in 20 days. Total work = 80 × 20 = 1600 man-days Step 2: Find time for 70 men Time = Total work / Number of men = 1600/ 70 Time = 22.86 days.