12 workers can complete a work in 18 days. How many days will 9 workers take?
Show answer
Correct answer A
Step 1: Total work = 12 × 18 = 216 work-days Step 2: Days for 9 workers = 216 ÷ 9 = 24.
Correct answer A
Step 1: Total work = 12 × 18 = 216 work-days Step 2: Days for 9 workers = 216 ÷ 9 = 24.