120 men can complete a work in 90 days. In how many days will 270 men complete the same work?

  • A45 days
  • B50 days
  • C40 days
  • D30 days
Show answerHide answer

Correct answer C

Work is inversely proportional to the number of men. So, (120 men × 90 days) = (270 men × x days) ⇒ 10800 = 270x ⇒ x = 10800 / 270 ⇒ x = 40 days.