If 5 workers can complete a task in 12 days, how many worker-days are required to complete the task?

  • A50 worker-days
  • B60 worker-days
  • C65 worker-days
  • DNone of these
Show answerHide answer

Correct answer B

Worker-days = Workers × Days = 5 × 12 = 60 worker-days.