If 5 workers can complete a task in 12 days, how many worker-days are required to complete the task?
Show answer
Correct answer B
Worker-days = Workers × Days = 5 × 12 = 60 worker-days.
Correct answer B
Worker-days = Workers × Days = 5 × 12 = 60 worker-days.