16 men dig a ditch in 10 days. The number of men required to complete the job in the half time?

  • A8
  • B32
  • C24
  • D20
Show answerHide answer

Correct answer B

16 men × 10 days = 160 man-days Half time = 10/2 = 5 days Men needed = 160 man-days / 5 days = 32.