16 men dig a ditch in 10 days. The number of men required to complete the job in the half time?
Show answer
Correct answer B
16 men × 10 days = 160 man-days Half time = 10/2 = 5 days Men needed = 160 man-days / 5 days = 32.
Correct answer B
16 men × 10 days = 160 man-days Half time = 10/2 = 5 days Men needed = 160 man-days / 5 days = 32.