8 machines can do a piece of work in 10 days. How long will it take 16 machines to do the work?

  • A05 days
  • B06 days
  • C07 days
  • D08 days
Show answerHide answer

Correct answer A

Work is constant: Machines × Days = Constant 8 × 10 = 80 machine-days For 16 machines: 80 ÷ 16 = 5 days.